Free 3-week look-ahead schedule
Plan the next three weeks by day: who's working what, how many people, and what has to happen first. Change one date and the whole calendar moves.
Excel or Google Sheets. Example rows are made up — clear them for your job.
What's in it
Questions
What is a 3-week look-ahead schedule?
A short-range schedule that breaks the next three weeks of the project schedule into daily activities by area, with the crew on each and what has to happen before it can start. Foremen update it every week.
What should a look-ahead include?
Each activity and area, the crew or foreman, the days it runs, how many people it needs, and its constraints — RFIs, submittals, deliveries, inspections or areas another trade must finish first.
How often should I update the look-ahead?
Every week, before the GC's coordination meeting: drop the finished week, add a new third week, and chase anything marked not ready.
Can I plan manpower across several jobs?
One sheet covers one job. Nucleus Command has a 4-week manpower plan across every job, so you see when two jobs want the same crew.
Done with spreadsheets?
Nucleus Command has a 4-week manpower plan across every job, so you see when two jobs want the same crew.
More free templates: Spec book → submittal register · T&M tag template · Change order log · All